Santiago's $3.8B Metro Line 7 Nears Completion, Reshapes Urban Transit
With construction 85% complete and a 2028 opening locked in, the data underpinning Chile's most ambitious urban transit project reveals both the scale of ambition and the pressure on public finances.
How we reported this

Construction on Santiago Metro's Line 7 has crossed the 85% completion threshold, metro operator Metro S.A. confirmed this week, keeping a 2028 inauguration date intact despite two years of supply chain disruptions and a contentious public spending debate in Congress. The line will stretch 26 kilometres from Renca in the northwest to Miraflores Alto in the east, threading through 19 stations and crossing some of the city's most congested corridors.
The timing matters. Greater Santiago adds roughly 100,000 new residents each year, a figure swollen further by Venezuelan and Haitian immigration concentrated in communes like Estación Central and Quilicura. The city's existing five metro lines carry approximately 2.4 million passengers per day, a number that, according to Ministerio de Transportes projections, will breach sustainable capacity by 2029 without new infrastructure. Line 7 is designed to absorb 800,000 daily trips at full operation.
What the Money Looks Like
The total project budget sits at 3.1 trillion Chilean pesos, roughly $3.8 billion USD at current exchange rates, making it the single largest public infrastructure contract in the country's history. Of that figure, approximately 68% is financed through sovereign bonds issued by the Ministerio de Hacienda, with the remainder drawn from a bilateral credit facility signed with the European Investment Bank in March 2024. Construction is split across three international consortia, with Spanish firm Acciona leading the central tunnel segment between Balmaceda and the Parque Bustamante station.
Civil works on the 4.2-kilometre underground section beneath Avenida Irarrázaval in Ñuñoa are the most advanced, sitting at 93% completion according to documents filed with the Contraloría General de la República in May. Above-ground viaduct sections near Lo Barnechea are lagging slightly at 78%, delayed by geological assessments required after minor subsidence was detected in late 2025. Metro S.A. says that gap will close by the first quarter of 2027.
Station architecture contracts were awarded to seven Chilean firms, a deliberate localization clause written into the original 2021 tender. The terminal at Plaza Egaña, which will serve as an interchange with Line 4, is expected to handle 45,000 passengers daily at peak, making it the busiest new node in the network. Engineers are installing platform screen doors across all 19 stations, a first for any Metro expansion line, at a unit cost of approximately 420 million pesos per station.
What the Commuter Actually Gets
For residents of Renca, a commune where median household income sits around 650,000 pesos per month and car ownership rates are among the lowest in the metropolitan region, Line 7 represents a direct connection to the financial district along Avenida Apoquindo without a transfer. Current bus routes via Transantiago, rebranded Red Metropolitana de Movilidad in 2021, take between 75 and 95 minutes during morning peak. Metro projections put the same trip at 32 minutes.
The adult single fare will be set under the existing integrated tariff structure, currently 810 pesos during peak hours, meaning Line 7 riders will pay no premium over existing network fares. Students and seniors holding the Tarjeta Nacional Estudiantil or pensioner concession cards will access the same 50% subsidy applied across the network.
Three more milestones sit between now and the 2028 opening. Electrical systems installation begins across the full route in September 2026. Rolling stock, 27 six-car trains manufactured by CAF in Spain, starts arriving at the Barrancas depot in Pudahuel in the second quarter of 2027. Revenue-service testing, mandatory under Chilean transport law for a minimum of six months, will run through the second half of 2027 before a commercial launch scheduled for March 2028. Commuters in Ñuñoa, Renca and Lo Barnechea are advised to track Metro S.A.'s official service bulletins, which are updated monthly on the metro.cl platform.